Standardisation

What if we stopped creating new project plans?


Story time – years ago, when I still had hair, I walked into a project management office inside a new Intel fabrication plant that was being built. Huge Gantt charts covering the walls, thousands of people involved, over a Billion Dollar cost. But the interesting bit – I learnt that they copy the plans, to the letter, from the last fab that was built, only changing where things failed. It’s a methodology that they called Copy Exactly, and it was designed to guarantee high volume production faster, and quick problem resolution. Bottom line – if it was successful, let’s stick to it.


Now, software delivery is not like building a fab, but here are some of my takeaways – When projects become standard and repeatable, we are rewarded with predictability and higher quality results. With standardisation knowledge becomes more evenly spread across teams. Standardisation is easier in a product-led organisation, the delivery teams do not need to rethink plans in order to cater for “but I also want this thing that my Excel does today…”. And finally, bespoke projects cost structures require a different methodology, usually dictating T&M pricing, or a detailed analysis first and only then budgeting and execution.

Back to my first question – no, we cannot always avoid new plans, but we can and should create templates and reuse what worked in the past.

Similar Posts

  • Data

    Blame the data (it can’t fight back) Is your team working extra hard, but you are still missing milestones? Chances are your data is lying to you.● Data quality: are the different teams/people logging all of the information in a timely manner and in the same way? Does a ticket ‘Completion Time’, for example, mean…

  • | |

    Expertise

    Is your expertise limiting your leadership? I was speaking with Shiri Yardeni this week (go read her posts for fresh perspectives), and at one point we discussed how our career paths led to different approaches to solving problems. In one of Shiri’s posts she explains that she is the one that is asking “the stupid…

  • |

    Proactivity

    Sometimes things don’t hurt enough until they hurt too much. Let’s get proactive and change that. We are creatures of adaptability, and when things get hard we grunt and we adjust and we carry on.I don’t particularly like pain, I like it even less if it’s avoidable. And in the world of enterprise software delivery…

  • Resource Management

    TL;DR – Resource management in scale-ups is hard, and there’s no magic wand. But piles of good accumulated data, and some standardised solutions and processes can get us most of the way there. Simples (right?) Deep breath, and here we go – In my experience, SaaS scale-ups often struggle with one or more of the…

Leave a Reply

Your email address will not be published. Required fields are marked *